Our Projects >> Capitol Expressway LRT GDC
![]() |
Description SAN JOSE, CALIFORNIA |
R&M Responsibilities
R&M responsibilities include overall team management, QA/QC program implementation, as well as design of roadway, retaining wall, utilities, drainage, signing, striping and construction staging plans. R&M is also preparing right of way requirements, utility relocation plans and cost estimate management.
Special Features
This project is the only extension of light rail transit underway in the San Francisco Bay Area. Prime Consultant managing 22 subconsultants for a 24 month final design process.
Copyright(c) 2007 Rajappan & Meyer Consulting Engineers, Inc. All Rights Reserved